Tesla Loadside Tap Example
BUSBAR SECTION Total 3 Busbars
BUSBAR 1 is the MSP (Main Service Panel)
On the 3-line diagram shown above it is the "Service Disconnect" (the Outdoor Meter/ Main Combo Service Panel). Below is an example of how to Declare in SolarAPP+
BUSBAR #2 - COMBINER PANEL (N) "INTERNAL BUSBAR FOR GATEWAY2:
Powerwall+ is landing the inverter and ESS loads on the internal panel board with a 50 amp OCPD (breaker) protecting it in the Tesla Gateway 2
BUSBAR #3 BACK-UP LOADS CENTER SUBPANEL
PCS SETTINGS
REMEMBER YOU SELECTED PCS AS YOUR TIE-IN METHOD IN BUSBAR 1 AKA THE MSP
Here we have set the PCS to comply with the limits of the 120% rule for a 200 amp bus with a 200 amp OCPD
200 * 1.2 = 240 - the main breaker rating = 40 AMPS OF AVAILABLE BACKFEED.
Set your PCS settings to 160 amps to keep the export within the 120% Rule
Contractor Resources:
TESLA MCI (Rapid Shutdown) Installation Manual
Important Tesla Model #'s
Powerwall 3 | 1707000-xx-y | |
Tesla Backup Gateway | 1232100-xx-y | |
Tesla Backup Switch | 1624171-xx-y | |
Powerwall 2 | 1092170-xx-y or 2012170-xx-y | |
Powerwall + | 1850000-xx-y | |
3.8kw Inverter | 1534000-xx-y | |
7.68 kW Inverter | 1538000-xx-y | |