How does SolarAPP+ incorporate Arc-fault requirements for conductors rerouted per 210.12.(d)?
The project application form asks the contractor if the relocated circuits extend more than 6ft. A 'yes' answer adds an item to the inspection checklist to verify the installation of Arc-fault circuit breakers per 210.12(d) of the NEC.