How does SolarAPP+ verify working clearances at permit issuance?

The inspection checklist contains a component for inspectors to confirm that the project is installed with working clearances. It states, "There is a minimum of 3' working clearance, according to the code, for all components that may require service.” Inspectors may fail a system that fails to meet this threshold. 

Still need help? Contact Us Contact Us