How does SolarAPP+ verify the location of service disconnects at permit issuance?

There are items in the fire bulletin and inspection checklist regarding disconnect location that the inspector must verify before a project is approved. The items are listed below:
  • “If connected equipment is NOT within line of sight or closer than 10ft to the point of interconnection, disconnect or isolation means are installed.”
  • “Disconnecting Means are in compliance with the SolarAPP+ Fire Bulletin.”

Still need help? Contact Us Contact Us